    <title>Frimley Fuel Allotments — Timeline of Events</title>
    <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
    <description>A fully sourced public records timeline tracking the proposed development of the Frimley Fuel Allotments woodland and Pine Ridge Golf Club for a new Frimley Park Hospital. Compiled from publicly available sources only.</description>
    <language>en-gb</language>
    <lastBuildDate>Thu, 20 Nov 2026 12:00:00 +0000</lastBuildDate>
    <atom:link href="https://ffawoodlandpreservation.github.io/Timeline/feed.xml" rel="self" type="application/rss+xml"/>

    <item>
      <title>18 November 2026 — FHFT&#8217;s JHOSC update paper claims full Gunning compliance — but the option was already signed before engagement opened, the evidence was withheld throughout, and the traffic surveys had yet to begin</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Ahead of the JHOSC meeting of 27 November 2026, FHFT submits a formal update paper asserting that its public engagement programme has met all four Gunning principles. Its compliance self-assessment does not survive scrutiny.

On Gunning Principle 1 — that proposals must be at a formative stage — the paper states "no final decision has been made." This claim is made without disclosing the most material fact: the option agreement to purchase 55 acres of FFA land was signed on 10 June 2026, six days before engagement opened on 16 June. At the moment the first member of the public was asked their view, the Trust had already paid £250,000 to the charity and held a binding legal right to acquire the site. The legal commitment pre-dated the engagement. The paper does not mention this.

On Gunning Principle 2 — that enough reasons must be given — the paper cites the engagement document, FAQs and 80-plus events. It does not mention that on 22 June 2026, while engagement was under way, Karin Smyth MP confirmed in Parliament that site selection criteria, site-specific costings and assessments of alternative sites would not be published because "publishing the details of this work... would risk prejudicing land negotiations." The material the public most needed to respond meaningfully was withheld, on commercial grounds, for the entire duration of the engagement.

The public were invited to comment on traffic and access impacts for which no completed evidence existed. The paper acknowledges traffic was "the concern raised most often" — then reveals the main traffic surveys will not begin until January 2027.

Before the ORS engagement report has even been published, the paper inserts a passage stating that "the popularity or unpopularity of draft proposals should not displace professional and political judgement" — pre-positioning the Trust to override the engagement findings on its own assessment of their "cogency." The paper also claims a telephone survey of 500 residents showed "a majority agreed with the proposed location" while acknowledging people within 5km "mostly disagreed, many of them strongly." The question wording is not disclosed. A "majority" of 500 interviews across a catchment of 500,000 people represents a minimum of 251 respondents — 0.05% of the population the Trust serves, or one person in every 2,000. The ±5 percentage point margin of error the paper itself acknowledges means the "majority" finding is statistically indistinguishable from 50/50. 251 people is a vanishingly small basis on which to claim majority public support for the most controversial NHS infrastructure decision in the region in decades.

The paper does not address the committee's formal resolution of 17 July 2026, which asked FHFT to "invest significantly to strengthen their communications." No account is given of compliance with that resolution.

The paper was published on 18 November 2026 — two days before the public question deadline for the 27 November meeting. Members of the public were given 48 hours to read, analyse and formulate a question from a 22-page technical document. The compressed window is itself inconsistent with the principle of genuine public involvement the paper claims to uphold.

Source: FHFT, "New Frimley Park Hospital: Update for the JHOSC, 27 November 2026" (Item 6, published 18 November 2026); cross-referenced against: Karin Smyth parliamentary answers 22 June 2026 (UINs 10384–10389); FFA Annual Accounts 2025, Note 24; JHOSC minutes 17 July 2026, minute 26/26; SHBC EPSC transcript 30 September 2026.]]></description>
      <pubDate>Wed, 18 Nov 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-11-18-fhft-jhosc-paper-gunning-analysis</guid>
    </item>

    <item>
      <title>7 April 2026 — FFA Charity still has not responded to EPSC invitation — three months on</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[At its April meeting (minute 18/EP), Surrey Heath's External Partnerships Select Committee notes that the FFA Charity has still not responded to the formal invitation issued in January 2026 — more than three months after it was sent pursuant to Full Council's resolution (minute 42/C). The next scheduled EPSC meeting is not until 30 September 2026, meaning FFA's continued failure to engage creates a six-month gap in formal scrutiny. Source: SHBC EPSC minutes, 7 April 2026 — minute 18/EP (surreyheath.moderngov.co.uk/mgAi.aspx?ID=22602).]]></description>
      <pubDate>Tue, 07 Apr 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-04-07-epsc-ffa-no-response</guid>
    </item>

    <item>
      <title>13 January 2026 — EPSC formally directs FFA Charity to attend — no response received</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Surrey Heath's External Partnerships Select Committee (EPSC) formally implements Full Council minute 42/C, directing the FFA Charity's Chair and Treasurer to attend a future EPSC meeting to account for the charity's undisclosed advisory relationship with Frimley Chilton Ltd, the developer seeking to build on its land. At the same meeting, EPSC also requests Surrey Wildlife Trust to give evidence on the ecological significance of the site. The committee records the invitation to FFA at minute 17/EP. The FFA Charity does not respond. Source: SHBC EPSC minutes, 13 January 2026 — minute 17/EP (surreyheath.moderngov.co.uk/mgAi.aspx?ID=22226).]]></description>
      <pubDate>Tue, 13 Jan 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-01-13-epsc-ffa-invitation</guid>
    </item>

    <item>
      <title>30 September 2026 — At SHBC scrutiny committee, Pinkerton states FFA is FHFT's own third-ranked site — and challenges Trust's refusal to use compulsory purchase powers to reach a better one</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Surrey Heath Borough Council's External Partnerships Select Committee met on 30 September 2026 with Dr Al Pinkerton MP attending. Under item 7, Pinkerton gave an extended account including detailed discussion of the proposed new Frimley Park Hospital. Pinkerton told the committee that the FFA site was not FHFT's preferred choice on its own assessment: "Frimley Fuel Allotments site is third on that list. It's not even the best site that they've identified, and they recognise that it's more environmentally damaging, more inaccessible than elsewhere." He continued: "because they say that they're not willing to use compulsory purchase powers because they have a willing seller... they're willing to go effectively for their third choice site. That suggests to me immediately that if they were willing to use compulsory purchase powers, there are two better sites than that they themselves have already identified." He challenged the Trust directly: "if ever I thought that compulsory purchase powers were appropriate, it would be to make sure that a hospital that we're going to be living with for 100 years is put in the right place." On the JHOSC scrutiny process, Pinkerton stated that "it was the chair and the vice chair who kind of unilaterally, working together, said 'yeah, go ahead guys, we're happy with what you're doing' — rather than going to the whole committee" — amounting to signing off on "what the public would understand to be a light-touch consultation." He further noted the engagement exercise was "not about the location of the hospital — it's about the nature of future healthcare," which "does not meet public expectations." Before the hospital discussion began, Democratic Services issued a formal predetermination warning that any discussion did not constitute the council's position as local planning authority. Councillor Shaun Garrett — appointed Chairman of Frimley Fuel Allotments Charity three months earlier — made a belated declaration of that interest once the charity was mentioned during discussion. Source: Surrey Heath Borough Council, External Partnerships Select Committee, 30 September 2026 — verbatim transcript (YouTube); Minutes published in EPSC report pack, 3 November 2026.]]></description>
      <pubDate>Tue, 30 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-30-epsc-pinkerton-cpow-third-site</guid>
    </item>

    <item>
      <title>7 November 2026 — JHOSC Chairman confirms Frimley Health management privately briefing committee members ahead of public scrutiny meeting</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[In his ward newsletter, JHOSC Chairman Trefor Hogg confirms that Frimley Health management have privately briefed committee members ahead of the 27 November public scrutiny meeting — a session held outside any public record or minute. Committee members will therefore arrive at the public meeting having already been briefed privately by the body whose proposals they are scrutinising. In December 2025, Hogg publicly championed independent NHS scrutiny, arguing that the NHS must not be allowed to "mark their own homework." The arrangement he describes is in tension with that principle. The same newsletter includes Hogg's own guidance on Biodiversity Net Gain, noting that sites containing priority habitats — such as the mature woodland at FFA, subject to a blanket Tree Preservation Order — cannot claim standard BNG exemptions. The question of how the development would meet its mandatory 10% biodiversity uplift requirement has not been raised by the JHOSC. Source: Trefor Hogg, Camberley East News, 7 November 2026.]]></description>
      <pubDate>Sat, 07 Nov 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-11-07-hogg-private-briefing</guid>
    </item>

    <item>
      <title>16 October 2026 — FFA — the charity created to hold the Frimley Fuel Allotments in trust — formally promotes the land for large-scale development</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Four days after FHFT's public engagement period closes, Frimley Fuel Allotments Charity — the body whose legal purpose is to hold the Frimley Fuel Allotments in trust for the benefit of the local community — submits a formal representation to Surrey Heath Borough Council's Local Plan Review 2040 Scoping Consultation requesting that the land be allocated for large-scale mixed development. The submission is signed by Chair Shaun Garrett. FFA's submission confirms, in plain terms, that the charity is no longer acting as a protector of the land: "FFA is promoting the residual land at Pine Ridge Golf Course for development via the Local Plan process. Land uses on the residual land are not yet determined." The justification offered is that FFA "is required to make best use of its assets." The community's open space has been reclassified — by its own trustee — as a development asset to be maximised. The submission asks SHBC to treat the land as a strategic site for the hospital plus "an appropriately planned mix of supporting development and infrastructure," encompassing housing, key-worker accommodation, specialist elderly housing and commercial uses. It asks that delivery of a new hospital be embedded in the Local Plan as a standalone Strategic Objective — seeking to lock the development into planning policy on a separate statutory track, independently of whether the FHFT programme is ever approved, funded or built. The submission repeatedly highlights that the land is not within the Green Belt, positioning it as a preferred development allocation ahead of Green Belt land elsewhere in the Borough. In a phrase that strips away any pretence that the development play depends on the hospital, FFA states explicitly that consideration of Pine Ridge for development "needs to come before wider Green Belt releases, regardless of whether the new hospital site is delivered." The land development is presented as independent of the hospital — it proceeds whether or not Frimley Health builds there. FFA also endorses the FHFT site selection process as having been "undertaken with rigour" — lending charitable legitimacy to a process directly contested by HWRA's site selection challenge letter of July 2026, to which FHFT never formally responded before engagement closed. In an admission that cuts against the thrust of its own submission, FFA acknowledges "the sensitivity of planning for change on a substantial development site" and flags the need for ecology, arboriculture, habitats and drainage surveys — the same environmental concerns underpinning HWRA's challenge throughout. The document that promotes the land for development simultaneously acknowledges the environmental case for protecting it. It does not use the words mature woodland anywhere in its text. Source: Frimley Fuel Allotments, Local Plan Review 2040 — Scoping Consultation Response, 16 October 2026 (ffa.charity/news/ffa-golf-course-local-plan-review-2040/).]]></description>
      <pubDate>Fri, 16 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-16-ffa-local-plan-submission</guid>
    </item>

    <item>
      <title>1 September 2026 — Ministry of Defence confirms land discussions with FHFT since 2022 — offers further talks on all local landholdings</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[In a letter to Dr Al Pinkerton MP, Minister for Defence Readiness and Industry Luke Pollard confirms that MOD officials have been engaging with the Department of Health and FHFT on the potential use of MOD land in the Frimley area since 2022. Discussions considered opportunities in Frimley, Aldershot and Sandhurst; no suitable land was identified for progression at that stage. The principal site of interest — the Frimley Cadet Training Centre, adjacent to the existing hospital — has consistently been assessed as unsuitable due to enduring military and training requirements, its Grade II listed status, and registered historic park and garden designations. However, following contact from the Trust in August 2026, MOD officials have offered to discuss all of their landholdings in the local area with the Trust. Source: Luke Pollard MP (Minister for Defence Readiness and Industry), letter to Dr Al Pinkerton MP, 1 September 2026 (ref MC2026/16619); published by Dr Al Pinkerton MP, Facebook, 9 November 2026.]]></description>
      <pubDate>Tue, 01 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-01-mod-pollard-land-discussions</guid>
    </item>

    <item>
      <title>February 2024 — Independent report confirms public never told which sites were under consideration — commercial confidentiality cited</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[DJS Research publishes its independent report on the November 2023–January 2024 public engagement, commissioned by Frimley Health. Of the 3,399 respondents, 72% were members of the public and 25% were FHFT staff. The report confirms that the public was asked to set evaluation criteria for unnamed sites. FHFT's own communications plan — appended to the report — states that naming specific sites was not possible due to "commercial considerations of confidentiality." Respondents who identified missing planning criteria most frequently cited availability of appropriate land, environmental impact, and the absence of protected sites or flood plains (35%) — factors that directly apply to the proposed FFA site, which includes mature woodland and sits adjacent to a gas pipeline hazard zone. Members of the public directly raised concern about the Army and Air Force currently using the site under consideration. The questionnaire itself noted that FHFT would additionally assess whether any site was on or near Green Belt land or Sites of Special Scientific Interest — but the public had no means to apply these criteria, as no sites were named. The report also confirms that Capsticks legal advice had been obtained in November 2023 — before the engagement even opened — that no formal public consultation was required. Source: DJS Research, Independent Engagement Report, February 2024 (commissioned by FHFT; available on FHFT new hospital document library).]]></description>
      <pubDate>Thu, 01 Feb 2024 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2024-02-djs-engagement-report</guid>
    </item>

    <item>
      <title>19 October 2026 — Information Commissioner rules FFA is not a public authority — environmental information requests must go to FHFT, SHBC or SCC</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[The Information Commissioner's Office issues Decision Notice IC-552032-P9N5, ruling that the Frimley Fuel Allotments CIO is not a public authority under the Environmental Information Regulations 2004. FFA declined to respond to an environmental information request about the site's natural greenspace value, stating it was not subject to EIR obligations. The ICO upholds that position. The practical consequence: environmental information about the FFA land — ecological surveys, habitat assessments, biodiversity data, natural greenspace designations — cannot be obtained from the charity by compulsion. All such requests must instead go to public authorities: Frimley Health NHS Foundation Trust, Surrey Heath Borough Council (as future local planning authority), or Surrey County Council. Source: Information Commissioner's Office, Decision Notice IC-552032-P9N5, 19 October 2026 (Environmental Information Regulations 2004).]]></description>
      <pubDate>Mon, 19 Oct 2026 00:00:00 +0000</pubDate>
      <guid>https://ffawoodlandpreservation.github.io/Timeline/#ico-decision-191026</guid>
    </item>

    <item>
      <title>21 March 2023 — Gove, Docherty and Sunderland write jointly to Health Secretary describing new-site build as "the Trust's preferred way forward"</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Michael Gove MP (Surrey Heath), Leo Docherty MP (Aldershot), and James Sunderland MP (Bracknell) write jointly to Health Secretary Steve Barclay offering "wholehearted support" for Frimley Health's £1.26bn New Hospital Programme bid. The letter describes a new-site build as "the Trust's preferred way forward" — adopting the Trust's own framing eight months before Frimley Health would open a public consultation on site selection criteria. At the time of writing, Gove is simultaneously the constituency MP for Surrey Heath and Secretary of State for Levelling Up, Housing and Communities, the government department responsible for national planning policy. HWRA meeting minutes record that around the same period, Gove is reported to have indicated to those with an interest in the process that Frimley Fuel Allotments was the likely site — before any formal site selection process had begun. Source: Michael Gove MP, Leo Docherty MP, James Sunderland MP, joint letter to Rt Hon Steve Barclay MP, 21 March 2023; HWRA meeting minutes, 3 July 2026.]]></description>
      <pubDate>Sat, 21 Mar 2023 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2023-03-21-gove-docherty-sunderland-letter</guid>
    </item>

    <item>
      <title>30 October 2026 — As McCarthy discourages formal letters, Pinkerton formally writes to the Secretary of State seeking clarification on the hospital's funding after a £957m procurement correction</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[On the same day FHFT Chief Executive Lance McCarthy writes to Dr Al Pinkerton MP encouraging him to use private phone calls rather than formal correspondence, Pinkerton writes formally to the Secretary of State for Health and Social Care, Yvette Cooper MP, seeking clarification on the procurement notice amendment filed two days earlier. The letter centres on a specific discrepancy: the Government's NHP implementation plan (January 2025) placed Frimley Park Hospital in the £1.5 billion to £2 billion estimated cost category, with around £1.8 billion understood to apply to the build itself. The 28 October amendment to the Hospital 2.0 Alliance contract — described only as "error identified by NHP" — records the corrected value as £1.043 billion, a reduction of nearly £957 million. Pinkerton also notes that separate procurement documents had listed the contract value at £200 billion. He asks four specific questions about the funding, scope, approved budget and any restrictions on hospital size or timetable, and calls for a published reconciliation of the procurement and programme figures. Sources: Dr Al Pinkerton MP, letter to the Rt Hon Yvette Cooper MP, Secretary of State for Health and Social Care, 30 October 2026; Al Pinkerton MP Facebook, 30 October 2026.]]></description>
      <pubDate>Fri, 30 Oct 2026 12:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-30-pinkerton-cooper-funding</guid>
    </item>

    <item>
      <title>30 October 2026 — Developer accidentally posts public endorsement of McCarthy letter — then deletes it after Pinkerton puts three questions on the public record</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[On 30 October 2026, Michael Riding — the Lancashire-based property developer who acted as land and marketing agent for the Frimley Fuel Allotments charity from February 2022 to April 2025, and who signed an NDA with the charity in July 2022 — comments publicly on Facebook: "Well spotted Simon — Lance has done a good job in composing that letter — it hits the spot perfectly. Regards Mike." Dr Al Pinkerton MP replies publicly, identifying Riding as "the land and marketing agent for Frimley Fuel Allotments via your company Frimley Chiltern Ltd." and noting he assumes Riding "meant to reply to 'Simon' privately." Pinkerton puts three questions on the public record: who "Simon" is; why Riding considers the McCarthy letter to have "hit the spot"; and whether the comment displays "a disturbing closeness between Frimley Park Hospital and the Frimley Fuel Allotments charity." Riding deletes his original comment shortly afterwards. The screenshot is preserved. Three questions remain unanswered. Source: Facebook, "Protect Frimley Fuel Allotments" group, 30 October 2026 — screenshot preserved.]]></description>
      <pubDate>Fri, 30 Oct 2026 12:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-30-riding-facebook-exchange</guid>
    </item>

    <item>
      <title>30 October 2026 — McCarthy concedes hybrid planning approach — and tells Pinkerton to stop writing letters</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[FHFT Chief Executive Lance McCarthy responds to Dr Al Pinkerton MP's letter of 21 October 2026. On planning, he confirms the Trust will pursue a hybrid planning application, stating an outline application "is not, and never has been, our preferred approach" — a concession to the position Pinkerton had explicitly pressed for. The Trust had not previously made this public. More strikingly, McCarthy tells Pinkerton to stop using formal correspondence: "I would again encourage you to raise questions like these directly with me or members of the programme team here, either by phone or at one of our regular meetings, rather than dealing with them through an exchange of letters." A formal letter from an MP to a public NHS body creates a record that can be published, submitted to scrutiny committees and verified. A phone call creates none of these things. McCarthy published this letter on FHFT's own website — putting on the public record his request that the MP should avoid doing the same. Source: Lance McCarthy, letter to Dr Al Pinkerton MP, 30 October 2026 — fhft.nhs.uk]]></description>
      <pubDate>Fri, 30 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-30-mccarthy-pinkerton-letters</guid>
    </item>

    <item>
      <title>2 October 2026 — As engagement runs, AECOM is appointed both project manager and cost consultant for the new hospital — the professional team for a settled site is complete</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Two F03 contract award notices published on 2 October 2026 — ten days before the public engagement closes — reveal that AECOM Limited has been appointed to two senior roles on the New Frimley Park Hospital programme, both via the HPCCAS framework without open competition. AECOM is appointed Cost Consultant (£477,891.94, awarded 23 September 2026) and Project Manager (£1,186,950, awarded 30 September 2026). Together with Arcadis (architect, appointed 13 August), Sacyr (construction contract signed 30 July), and the planning and legal tenders already published, this completes the core professional team required to develop, design, and obtain planning permission for a specific site. The combined value of appointments made before the engagement closed exceeds £9 million. Professional teams of this kind are appointed for named projects on defined sites — not to explore whether a site might be chosen. When McCarthy told ITV on 13 October that the site was "absolutely" still open to challenge, the project manager and cost consultant had each been in post for nearly a fortnight. Sources: Find a Tender, Notice 2026/S 000-093424 and Notice 2026/S 000-093426, published 2 October 2026.]]></description>
      <pubDate>Fri, 02 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-02-aecom-dual-appointment</guid>
    </item>

    <item>
      <title>16 September 2026 — FHFT tenders £1 million planning lawyers contract — with bids accepted on the day the engagement exercise closes</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Nine days after publishing the town planner tender, FHFT publishes a contract for specialist town planning legal advice (Notice 2026/S 000-087608), estimated at £1,000,000 excluding VAT. The scope covers the full legal apparatus to obtain planning permission: planning applications, EIA and HRA legal advice, Section 106 negotiation, and — explicitly — "judicial review and statutory challenge advice under the Town and Country Planning Act 1990." The tender submission deadline was 12 October 2026 — the final day of the public engagement exercise. Legally binding bids from law firms were accepted at the same moment the Trust closed the public inbox. The following day, 13 October, McCarthy was asked by ITV whether the site location was "still genuinely open to challenge" and answered: "Yes, absolutely." A planning consent process cannot be underway for a site that has not been chosen. Source: Find a Tender, Notice 2026/S 000-087608, published 16 September 2026.]]></description>
      <pubDate>Wed, 16 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-16-planning-legal-tender</guid>
    </item>

    <item>
      <title>7 September 2026 — On the day of its public engagement webinar, FHFT publishes a tender for a seven-year town planning contract — including Environmental Impact Assessment and Habitats Regulations Assessment for the FFA site</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[On the same day that Frimley Health holds its public engagement webinar, the Trust publishes a formal tender notice on the government's Find a Tender register (Notice 2026/S 000-084205) seeking a provider for "the provision of town planning services in connection with the New Frimley Park Hospital programme." The scope covers the full planning consent pipeline including EIA co-ordination, Habitats Regulations Assessment, Section 106 negotiation, and post-consent support — statutory processes triggered by a settled development proposal, not a live deliberation. The contract runs from 24 November 2026 to 31 December 2033 (seven years). The tender submission deadline was 7 October 2026, five days before the engagement exercise closed on 12 October. Award decision date: 4 November 2026. Estimated contract value: £221,000 excluding VAT. Source: Find a Tender, Notice 2026/S 000-084205, published 7 September 2026.]]></description>
      <pubDate>Mon, 07 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-07-town-planner-tender</guid>
    </item>

    <item>
      <title>28 October 2026 — NHS England quietly corrects Frimley hospital contract notice after £957m error — official government register confirms £1.043bn contract, with just £3.4m currently authorised</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Seven days after Frimley Health NHS Foundation Trust publishes the formal contract award notice for the new hospital on the government's Find a Tender register — filing the contract value at £2,000,000,000 — the New Hospital Programme files two amendment releases on 28 October 2026, correcting the figure to £1,043,000,000. The difference is exactly £957,000,000. The reason given on the official government procurement register: "Error identified by NHP." The original notice also listed the lowest and highest bid as £200,000,000,000 — two hundred billion pounds — a separate error on the same document. The corrected notice confirms that only £3,404,000 is currently authorised (Stage Zero advisory works); the £1.043bn headline figure requires further Notices to Proceed for Stages One and Two before any building can begin. Source: UK government procurement register, OCDS release package ocds-h6vhtk-044e56, 28 October 2026; Construction News, 29 October 2026.]]></description>
      <pubDate>Wed, 28 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-28-sacyr-contract-error</guid>
    </item>

    <item>
      <title>21 October 2025 — Developer&#39;s &quot;Frimley Park Village&quot; company dissolved — 11 months after incorporation drew campaign attention</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Frimley Park Village Ltd (Companies House 16057535) — registered by Michael Riding's corporate group on 4 November 2024 — is dissolved after just 11 months. The company's name explicitly anticipated residential development of the existing Frimley Park Hospital site on Portsmouth Road: land that would only become available for housing if NHS Frimley Health first relocated its hospital onto the Frimley Fuel Allotments. The timing of the dissolution is consistent with the company name having attracted attention from campaigners. HWRA researchers had by this point identified and documented the incorporation as evidence of the developer's commercial interest in the vacated hospital site — an interest undisclosed in FFA's published accounts and never raised before SHBC's scrutiny committee. Source: Companies House, Frimley Park Village Ltd (16057535).]]></description>
      <pubDate>Tue, 21 Oct 2025 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2025-10-21-frimley-park-village-dissolution</guid>
    </item>

    <item>
      <title>9 December 2025 — JHOSC Chair warns NHS scrutiny "catastrophe" if independent oversight abolished — calls letting NHS assess itself "marking their own homework"</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[At a meeting of Surrey County Council's Adult and Health Select Committee, Cllr Trefor Hogg — who chairs both that committee and the JHOSC responsible for scrutinising the Frimley Park Hospital relocation — moves a motion calling on the DHSC to reverse its plans to abolish local Healthwatch organisations. The motion passes unanimously with full cross-party support. Hogg warns that without independent patient representation, NHS and social care services "will not face proper scrutiny in the future" and that ministers will be able to "mark their own homework." He describes the loss of independent local oversight as "a catastrophe in the making." Seven months later, as JHOSC Chair for the FFA scrutiny process, Hogg pre-shares his committee's questions with NHS representatives privately before public meetings, co-signs a letter on behalf of the JHOSC without committee authority to prevent formal public consultation, and dismisses campaign concerns as "misplaced claims" — conduct that the SCC Monitoring Officer subsequently confirms exceeded his authority. Source: Trefor Hogg, Facebook post, 9 December 2025; BBC Surrey, Jack Fiehn, 15 December 2025.]]></description>
      <pubDate>Tue, 09 Dec 2025 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2025-12-09-hogg-healthwatch</guid>
    </item>

    <item>
      <title>10 June 2026 — Formal option agreement signed — FHFT pays £250,000 option fee to FFA charity</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[On 10 June 2026, the Frimley Fuel Allotments CIO formally enters into a conditional option agreement for the sale of part of its land to Frimley Health NHS Foundation Trust, together with a related conditional agreement to acquire the surrender of the leasehold interest over that land — the Pine Ridge Golf Centre lease. On signing, the charity receives an option fee of £250,000. The fee will be set against the sale price if the sale completes. If the agreement ends before completion — for example, if planning permission is refused — the FFA must repay the fee, but may first deduct its legal, surveying and agency costs. The deposit is therefore not fully refundable: FHFT may not recover the full £250,000 if planning is refused. The signing takes place eight days after the JHOSC meeting of 2 June 2026, at which FHFT had presented an option agreement as a completed milestone ("February to May 2026"), and six days before FHFT's public announcement of the FFA site on 16 June 2026. The option fee does not appear in either organisation's most recent published accounts; FHFT's 2025–26 Annual Report contains no reference to the FFA, the option agreement, or the deposit anywhere in its 180 pages. Source: FFA Annual Accounts 2025, Note 24 (Post Balance Sheet Events), filed Charity Commission 28 October 2026 (charity number 1161717).]]></description>
      <pubDate>Wed, 10 Jun 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-06-10-option-agreement-signed</guid>
    </item>

    <item>
      <title>22 June 2026 — Government answers confirm Frimley Park is the only Wave 1 hospital being relocated away from its existing site — and that site scoring was rerun at NHP officials&#8217; request</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[On 16 June 2026 — the same day Frimley Health publicly announces the Frimley Fuel Allotments as its preferred site — Dr Al Pinkerton MP tables six written questions to the Secretary of State for Health and Social Care. He asks whether the full site selection criteria, the site-specific costings for each option, and the assessments of alternative sites (including land adjacent to the existing hospital) will be published; what assessment has been made of environmental impact; what discussions the Department has had with Surrey County Council on road capacity and access; and whether the Department has reviewed the scoring for each site considered.

Karin Smyth, Minister of State for Health and Social Care — quoted in FHFT's own preferred site press announcement six days earlier — answers on 22 June. Her responses, published in the House of Commons Written Questions Daily Report, make three significant admissions on the public record.

The government refuses to publish the site selection criteria, the site-specific costings, or the assessments of alternative sites: "Publishing the details of this work, including site-specific assessments and costings, would risk prejudicing land negotiations and exposing the public purse to avoidable costs." No prior environmental assessment and no prior Surrey CC transport discussions are confirmed. These will instead be matters for the statutory planning process — meaning the evidence the public needed to scrutinise before engagement closed was deliberately withheld, on commercial grounds, throughout the engagement period.

The government twice confirms the site selection process was rerun: "This included, at the request of NHP officials, a rerunning and blind scoring of all sites identified as suitable for the new hospital to ensure that no prejudgement had taken place." The fact that it was NHS programme officials themselves who requested the rerun implies the original scoring was considered potentially flawed or susceptible to challenge.

In a separate answer (UIN 10389), the government publishes a table of all Wave 1 New Hospital Programme schemes listing whether each is planned on or adjacent to its existing site. Of fourteen named hospitals, Frimley Park is the only one classified as "on and non-adjacent to existing site." Every other Wave 1 hospital — Cambridge Cancer Research, Derriford, Hillingdon, Hinchingbrooke, James Paget, Leighton, Milton Keynes, North Manchester, Poole, Queen Elizabeth King's Lynn, Shotley Bridge and West Suffolk — is being rebuilt on or adjacent to its existing site. The government's own parliamentary answer confirms that relocating Frimley Park to a non-adjacent greenfield site is not standard practice across the New Hospital Programme: it is the exception, and the sole exception.

Smyth also states: "No final decision has been made on the location for the new Frimley Park Hospital." This is the government's formal parliamentary position on 22 June 2026 — five days after FHFT's public preferred site announcement and twelve days after the option agreement was signed.

Source: Written Questions, Answers and Statements, House of Commons Daily Report, 22 June 2026 — UINs 10384, 10385, 10386, 10393, 10396, 10397, 10389 (questions-statements.parliament.uk; answered by Karin Smyth, Minister of State for Health and Social Care)]]></description>
      <pubDate>Mon, 22 Jun 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-06-22-parliamentary-answers-nhp-wave1</guid>
    </item>

    <item>
      <title>24 December 2025 — FFA trustee publicly denies any formal sale agreement — while bound by NDA on ongoing negotiations</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Writing to a local resident on Christmas Eve 2025, Councillor Murray Rowlands states that "nothing has been decided about whether a sale of the Fuel Allotment's land at Pine Ridge will take place" and that "there has not been a formal offer nor has the Trust moved to accept any offer to alienate its land to Frimley Park Hospital." Rowlands also states that only a "small part" of the allotment would be used for construction and car parking — a characterisation at odds with the Trust's own engagement materials, which describe a 55-acre development footprint in a predominantly wooded site. At the time of writing, Rowlands had been an FFA trustee since June 2023. The FFA trustees had been party to a non-disclosure agreement with Frimley Health since at least November 2023, and option agreement negotiations were at an advanced stage — though no formal agreement had yet been executed. On the statutory record, the formal conditional option agreement was signed on 10 June 2026 — more than five months after this letter. Rowlands' statement that "there has not been a formal offer" was technically accurate at the date of writing. His broader claim that "nothing has been decided" sits less comfortably with the state of negotiations he must, as a trustee, have known about — negotiations that would result in a signed legal agreement and a £250,000 payment to the charity within six months. Source: Councillor Murray Rowlands, letter to local resident, 24 December 2025.]]></description>
      <pubDate>Wed, 24 Dec 2025 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2025-12-24-rowlands-letter</guid>
    </item>

    <item>
      <title>July 2026 — School trust formally objects to Pine Ridge — warns process has "reached a conclusion before key questions have been fully assessed"</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Engage Enrich Excel Academies Trust (EEEA) — whose schools include Ravenscote Junior School, the educational setting closest to the proposed site — writes formally to Frimley Health raising significant concerns. The letter warns that the selection process "appears to have reached a conclusion before key questions relating to road capacity, emergency access, school travel, pedestrian safety and infrastructure requirements have been fully assessed." On community engagement, EEEA states that "the limited engagement to date risks creating the perception that consultation is being undertaken to support a preferred outcome rather than genuinely shape the decision-making process." The letter cites Chobham Road and Old Bisley Road as already experiencing significant congestion during school hours, with the road network becoming "effectively gridlocked" during M3 incidents. Source: Engage Enrich Excel Academies Trust, letter to Caroline Hutton, Frimley Health NHS Foundation Trust, July 2026.]]></description>
      <pubDate>Wed, 01 Jul 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-07-eeea-letter</guid>
    </item>

    <item>
      <title>21 October 2026 — McCarthy publicly confirms Frimley Fuel Allotments as preferred site in open letter to Surrey Heath school leaders</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[FHFT Chief Executive Lance McCarthy publishes a formal response to Surrey Heath school leaders on the Trust's own website — the first time FHFT has confirmed the designation in its own words on a public-facing platform: "Land currently occupied by Pine Ridge Golf Club, owned by local charity Frimley Fuel Allotments, is our preferred site." McCarthy frames "preferred site" as a Green Book process term, notes it is not a final decision, and states it follows a review of 18 other sites and two rounds of independent analysis. He confirms a third-party consultant is carrying out transport analysis this autumn and winter working directly with headteachers. He acknowledges school leaders remain opposed — "you remain opposed to the site, and there is more work to do together" — and adds: "I also recognise that your experience of our discussions to date may differ from how they have been described publicly." Source: Lance McCarthy, open letter to Surrey Heath school leaders, 21 October 2026 (fhft.nhs.uk).]]></description>
      <pubDate>Wed, 21 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-21-mccarthy-school-leaders</guid>
    </item>

    <item>
      <title>21 October 2026 — Pinkerton writes to McCarthy urging hybrid planning application — warns outline route would defer "potentially determinative" questions on site viability</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Dr Al Pinkerton MP writes to FHFT Chief Executive Lance McCarthy urging the Trust to submit a hybrid planning application rather than a wholly outline one. Pinkerton argues that transport, access and highways are not secondary reserved matters — they go directly to whether Frimley Fuel Allotments is a viable location at all. A wholly outline application would allow the principle of development to be established while deferring the most consequential questions to later reserved matters applications. Pinkerton warns: "The planning process should be the point at which those questions are exposed to proper scrutiny — not a mechanism through which they are deferred." Source: Dr Al Pinkerton MP, letter to Lance McCarthy, 21 October 2026.]]></description>
      <pubDate>Wed, 21 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-21-pinkerton-hybrid-planning</guid>
    </item>

    <item>
      <title>17 October 2026 — Hogg newsletter admits access problems "undoubtedly real and present right now"</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[JHOSC Chair Cllr Trefor Hogg's ward newsletter confirms that the Transport and Access Study for the FFA site is only now "getting under way," with winter data still needed. He writes that access problems are "undoubtedly real and present right now" — directly contradicting his co-signed letter to NHS Frimley ICB of 4 July 2025, which asserted there would be "no negative impact on access." That letter was cited by the ICB when resolving not to undertake public consultation — a resolution the SCC Monitoring Officer has since confirmed was issued without authority and carried "no weight." The newsletter also confirms the scheme is moving from Strategic Outline Case to Outline Business Case stage, and that land purchases are expected before the Full Business Case is approved. Source: Trefor Hogg ward newsletter, 17 October 2026.]]></description>
      <pubDate>Sat, 17 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-17-hogg-newsletter</guid>
    </item>

    <item>
      <title>14 October 2026 — SHBC Leader confirms monitoring officer ruled JHOSC letter had "no weight"</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[At Surrey Heath Borough Council's Full Council meeting, Council Leader Cllr Shaun Macdonald states that FHFT is "playing a little bit fast and loose with the facts" on school engagement. He then makes a statement of major legal significance: "The monitoring officer from Surrey County Council has confirmed that the chair and vice chair had no such authority to write on behalf of that body and therefore that letter had no weight in the decision-making process." The letter — co-signed by JHOSC Chair Cllr Trefor Hogg and Vice-Chair Cllr Carla Morson — was used by NHS Frimley ICB as the basis for its July 2025 resolution not to undertake public consultation. Macdonald also warns that if the proposal proceeds, "there will, on a mathematical and risk basis, there will be fatalities and serious injuries." Source: SHBC Full Council, 14 October 2026.]]></description>
      <pubDate>Wed, 14 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-14-shbc-leader</guid>
    </item>

    <item>
      <title>13 October 2026 — ICO rules FHFT breached environmental information law on the day engagement closes</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[The Information Commissioner's Office issues Decision Notice IC-567662-H7C3 finding that Frimley Health NHS Foundation Trust breached Regulation 5(2) of the Environmental Information Regulations 2004 by failing to respond within 20 working days to a request for all documentation, environmental reports, traffic and infrastructure reports, and risk maps relating to the site decision — submitted on 15 June 2026, the day before the preferred site was publicly announced. The ICO orders FHFT to provide a substantive response within 30 calendar days. Failure to comply may be treated as contempt of court. The notice is issued on the same day the 17-week public engagement closes — meaning residents completed their responses without access to documentation the Trust was legally required to disclose. Source: ICO Decision Notice IC-567662-H7C3, 13 October 2026.]]></description>
      <pubDate>Tue, 13 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-13-ico-decision</guid>
    </item>

    <item>
      <title>13 October 2026 — FHFT confirms 10,000 responses as 17-week engagement closes — planning application and JHOSC scrutiny timetable set</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Frimley Health NHS Foundation Trust announces the close of its 17-week public engagement on 12 October 2026, confirming more than 10,000 responses across 23 postcode areas in Surrey, Hampshire and Berkshire. An independent analysis by Opinion Research Services (ORS) is now underway; findings are to be published in a report later this year and presented to the Joint Health Overview and Scrutiny Committee at the end of November 2026. FHFT confirms a planning application is planned for autumn 2027, with national approvals and detailed business cases required before any construction can begin. Traffic surveys will be carried out over the coming winter. Chief Executive Lance McCarthy acknowledges that feedback included "concerns about issues such as traffic at the preferred location" and commits to working with communities to "develop solutions to areas of concern and challenge." Source: FHFT, "Public engagement on proposals for a new Frimley Park Hospital comes to a close," 13 October 2026 (fhft.nhs.uk).]]></description>
      <pubDate>Tue, 13 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-13-fhft-engagement-closure</guid>
    </item>

    <item>
      <title>13 October 2026 — Pinkerton tells ITV of 50-acre sites "not even considered" — McCarthy confirms surveys still outstanding</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[ITV News broadcasts a report on the proposed new Frimley Park Hospital. CEO Lance McCarthy confirms traffic, transport and ecological surveys have not yet been completed. Dr Al Pinkerton MP tells ITV he is aware of "50 acre sites, which is what they claim they need, that haven't even been considered" — directly challenging the credibility of the 18-site selection process. When pressed whether the location is "still genuinely open to challenge," McCarthy answers: "Yes, absolutely." Source: ITV News, 13 October 2026.]]></description>
      <pubDate>Tue, 13 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-13-itv-news</guid>
    </item>

    <item>
      <title>8 October 2026 — Windlesham Parish Council warns communities must not become "rat-runs" — criticises late engagement</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Windlesham Parish Council submits a formal consultation response on behalf of the communities of Bagshot, Lightwater and Windlesham. Without opposing the principle of a new hospital, the Council raises significant concerns on transport and engagement. It demands traffic modelling covering the A322/M3 Junction 3 interchange, peak-period conditions, long-term demand, and displacement through all three villages, warning they "must not become rat-runs." It states that reduced car dependency must not substitute for proper road capacity assessment. On engagement: "That has not been our experience" — and: "Communication should not simply be about explaining decisions that have already been made." Source: Windlesham Parish Council, consultation response, 8 October 2026.]]></description>
      <pubDate>Thu, 08 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-08-windlesham-pc</guid>
    </item>

    <item>
      <title>12 October 2026 — 36 schools and 13,000 pupils: updated joint statement opposes FFA site on day engagement closes</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[On the day the public engagement exercise closes, school leaders from more than 36 schools covering 13,000+ pupils issue an updated joint statement opposing the FFA site. Their message: "We support the urgent delivery of a new Frimley Park Hospital. We do not support the Frimley Fuel Allotments site." The statement directly contradicts FHFT's public claim of close collaboration with schools: "public statements have suggested there has been close collaboration with school leaders when this has not reflected our experience." Dr Al Pinkerton MP says the case for the FFA site "has not been made." Sources: Local School Leaders joint statement; Al Pinkerton MP, Facebook, 12 October 2026.]]></description>
      <pubDate>Mon, 12 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-12-school-statement</guid>
    </item>

    <item>
      <title>12 October 2026 — Public engagement closes — 10,000+ responses received, but traffic study has not yet started</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[The 17-week public engagement exercise closes. CEO Lance McCarthy tells BBC Radio Berkshire the programme received over 10,000 questionnaire responses. He confirms detailed traffic and transport analysis will not begin until November 2026 — after the engagement has closed — meaning residents raised transport concerns without access to any completed transport modelling for the site. HWRA members are quoted by BBC Surrey highlighting dangers to pedestrians and the community value of the woodland. Sources: BBC Radio Berkshire; BBC News, 12 October 2026.]]></description>
      <pubDate>Mon, 12 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-12-engagement-closes</guid>
    </item>

    <item>
      <title>7 October 2026 — FHFT's final engagement email confirms ORS will "not make recommendations or decisions"</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Four days before the engagement deadline, FHFT distributes an email confirming that Opinion Research Services (ORS) will prepare a report but will not make recommendations or decisions on the site. This directly contradicts FHFT's own FAQ, which states the site choice is "not final." The email also introduces the Green Book framework as reassurance — drawing attention to the fact that no business case has yet been approved. Source: FHFT email to members, 7 October 2026.]]></description>
      <pubDate>Wed, 07 Oct 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-10-07-ors-email</guid>
    </item>

    <item>
      <title>29 September 2026 — CEO Facebook reel responds to "key issues raised" — five claims warrant scrutiny</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[CEO Lance McCarthy publishes a video responding to key issues raised about the proposed hospital. Analysis of the verbatim transcript identifies five claims that warrant scrutiny: a false dichotomy on the current site, unconfirmed funding presented as secured, an "independently assured" process with no assurance report published, a geographically misleading "closer to home" claim, and a framing that confirms the decision is treated as already made. Source: FHFT Facebook, 29 September 2026.]]></description>
      <pubDate>Tue, 29 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-29-ceo-reel</guid>
    </item>

    <item>
      <title>26 September 2026 — JHOSC Chair's newsletter reports Annual Members' Meeting as promotional content — omits deprivation admission</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[JHOSC Chair Cllr Trefor Hogg's ward newsletter reports attending the Annual Members' Meeting but omits FHFT's own admission that a rival site scored better on deprivation. The newsletter also states the RAAC deadline as "by 2025" — a year that has passed and a date that appears in none of FHFT's official materials. Source: Trefor Hogg ward newsletter, 26 September 2026.]]></description>
      <pubDate>Fri, 26 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-26-hogg-newsletter</guid>
    </item>

    <item>
      <title>22 September 2026 — At Annual Members' Meeting, FHFT concedes a better site for deprived communities existed — but was set aside</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[At FHFT's Annual Members' Meeting, a slide states: "One shortlisted site scored better on deprivation, but it could not be delivered because of size, aviation and ownership constraints." This is a formal, on-the-record concession that the Frimley Fuel Allotments is not the site best placed to serve communities with the highest health need. The evidence for setting aside the better-scoring site has not been published. Sources: FHFT Annual Members' Meeting, 22 September 2026.]]></description>
      <pubDate>Tue, 22 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-22-amm-deprivation</guid>
    </item>

    <item>
      <title>21 September 2026 — FHFT maildrop reaches local households — proposed site not mentioned</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Frimley Health distributes an engagement postcard to households across its catchment area inviting residents to complete a questionnaire. The leaflet does not mention the Frimley Fuel Allotments, does not state that a preferred site has already been chosen, and does not mention woodland, green belt or the charity status of the land. Residents completing the exercise in good faith had no basis on which to assess the proposal's implications. Source: FHFT engagement postcard, received September 2026.]]></description>
      <pubDate>Mon, 21 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-21-maildrop</guid>
    </item>

    <item>
      <title>18 September 2026 — CEO video rules out current site — contradicting FHFT's own record</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[CEO Lance McCarthy publishes a Facebook Reel stating the current site rebuild "wouldn't be complete by 2035" and that planning consent is "unlikely." Three things directly contradict this: (1) the government's independent assessment found FPH's RAAC planks serviceable to approximately 2040; (2) FHFT itself received planning approval for a four-storey building on the existing site in March 2023; (3) FHFT's own Site Selection Report shows FFA scored third out of four sites. Sources: Facebook Reel, Lance McCarthy, 18 September 2026; Mott MacDonald/DHSC, December 2025; SHBC planning records.]]></description>
      <pubDate>Thu, 18 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-18-ceo-video</guid>
    </item>

    <item>
      <title>12 September 2026 — Hundreds march in protest at FFA site choice</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[Hundreds of residents attend a peaceful protest walk organised by the Heatherside Ward Residents' Association (HWRA), gathering outside the existing Frimley Park Hospital. Dr Al Pinkerton MP attends. An HWRA spokesperson states: "The Trust's own experts ranked it third of four, and worst for the environment, yet it became the preferred choice." Sources: Surrey Live, 14 September 2026; Dr Al Pinkerton MP, Facebook, 14 September 2026.]]></description>
      <pubDate>Sat, 12 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-12-protest-march</guid>
    </item>

    <item>
      <title>7 September 2026 — HWRA meets FHFT leadership — CEO apologises for engagement failures; CPO contradiction exposed</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[HWRA representatives meet CEO Lance McCarthy, SRO Caroline Hutton and Programme Director Alex White at Frimley Park Hospital. Key disclosures: McCarthy apologises more than once for not getting the engagement right. NHS England is confirmed to have reviewed and re-run the site selection process. FHFT acknowledges that compulsory purchase orders may be needed for transport — directly contradicting its stated rationale for selecting the site. FHFT confirms large areas of woodland would need to be removed. Source: HWRA Notes of meeting with FHFT, published 30 September 2026.]]></description>
      <pubDate>Sun, 07 Sep 2026 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2026-09-07-hwra-fhft-meeting</guid>
    </item>

    <item>
      <title>6 September 2024 — Transport assessment completed and given to County Highways — junctions already at capacity</title>
      <link>https://ffawoodlandpreservation.github.io/Timeline/</link>
      <description><![CDATA[At the September 2024 JHOSC meeting, Interim Programme Director Cain Thomas discloses that a transport assessment has been completed and submitted to Surrey County Highways. The assessment finds that junctions near the preferred sites are "at capacity and requiring significant infrastructure upgrades." Thomas states the cost of road upgrades "would be part of the new funding envelope." The assessment has never been published. A request for its release has been submitted under the Environmental Information Regulations 2004. Sources: JHOSC minutes, 6 September 2024; Surrey CC Highways (EIR request submitted).]]></description>
      <pubDate>Fri, 06 Sep 2024 00:00:00 +0000</pubDate>
      <guid isPermaLink="false">ffa-timeline-2024-09-06-transport-assessment</guid>
    </item>